Sbts objects of the chemical industry. Directory of basic prices for design work for the construction of chemical fiber industry facilities. Basic prices for the development of project documentation

FEDERAL CONSTRUCTION AGENCY
AND HOUSING AND COMMUNAL SERVICES

BASIC PRICE GUIDE
FOR DESIGN WORK FOR CONSTRUCTION

INDUSTRIAL FACILITIES
CHEMICAL FIBERS

MOSCOW2004

Directory of basic prices for design work for construction “Chemical fiber industry facilities”» 2004

DEVELOPED BY FSUE "CENTRINVESTproject" (Puliko V.I., Turenskaya M.A., Bortnikova E.S.) and JSC "Giproiv" (Yushchenko V.V., Zharova V.R.).

CONSIDERED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia (Stepanov V.A., Grishchenkova T.L.).

INTRODUCED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia.

ADOPTED AND ENTERED INTO EFFECT on May 15, 2004 by letter of the Federal Agency for Construction and Housing and Communal Services dated May 7, 2004 No. AP-2642/10 in agreement with the Department of Industrial and Innovation Policy in the Chemical Industry of the Ministry of Industry, Science and Technology Russian Federation dated April 21, 2002 No. 14-248.

IN REPLACE for Chapter 5 “Sub-industry of chemical fibers and threads” and Chapter 14 “Ancillary and service facilities, on-site networks and structures of water supply, sewerage, heat supply and electricity” of Section 9 “Chemical industry” of the Collection of prices for design work for construction ed. 1987 with amendments and additions 1988 - 1990

Explanations and consultations on the application of this Handbook are provided by FSUE "CENTRINVESTproject" ( 125057 , G. Moscow, Leningradskyetc., 63 , tel. (095 ) 157 - 39 - 42 ) and JSC "Giproiv" ( 141009 , G. MytishchiMoscowregion., st. CarlaMarx, 4 , tel. (095 ) (583 - 33 - 81 ).

1 main provisions. 1

2 basic prices for the development of project documentation. 4

Chapter 1 Objects of main, auxiliary and general plant purposes. 6

Table 1 Main production facilities. 6

Table 2 Repair services.. 19

Table 3 Objects for auxiliary production, auxiliary and general plant purposes, on-site engineering networks, general plan. 22

Table 4 Treatment facilities and water blocks. 33

Table 5 Transformer substations and switchgears located at fire and explosion hazardous production sites. 36

Chapter 2 Special sections of design documentation for construction. 40

Table 6 Industrial safety. 40

Table 7 Additional work on industrial safety. 40

Table 8 Drawing up initial requirements for the development of new custom-made technological equipment. 41

1 BASIC POINTS

1.1 The Directory of base prices for design work for construction (hereinafter referred to as the “Directory”) is recommended for determining base prices for the purpose of subsequent formation of contract prices for the development of design documentation for the construction of chemical fiber industry facilities: production facilities, complexes, individual facilities for auxiliary production and auxiliary purposes , special sections of the project.

1.2 Basic prices in the Directory are set depending on the natural indicators of the designed objects: area, productivity, capacity, etc., or for objects as a whole.

1.3 When using this Directory, you should take into account the General instructions for the use of Directories of basic prices for design work for the construction of ed. 2002

1.4 The price level contained in the tables of the Directory is established as of 01/01/2001.

1.5 In addition to the work listed in clause 7 of Section I of the General Guidelines for the use of Directories of basic prices for design work for construction, the basic prices of the Directory do not take into account:

· development of design documentation for individual production of switchboards, cabinets and control panels for electrical systems and automation systems;

· development of technological regulations for the production of products;

· design of energy consumption accounting and control systems;

· design of experimental, pilot-industrial production, workshops, installations, lines;

· design of fire extinguishing systems, fire and security alarms, warning people about a fire;

· technical support of construction;

· development of automated dispatch and control systems for energy supply (ASUE), development of a process control algorithm (PCA) and emergency protection (EPS);

· development of a project for the transportation of large-sized heavy equipment;

· design of a sanitary protection zone;

· development of thermal insulation;

· production and additional sending to the customer of project documentation on electronic media (floppy disks, CDs, etc.):

· development of a three-dimensional electronic model of pipelines and equipment, ventilation systems, instrumentation and automation routes and electrical cables, load-bearing building structures;

· development of industrial television projects;

· development of the “Declaration of Industrial Safety” and examination of the “Declaration of Industrial Safety”;

· development of measures for the restoration (reclamation) of land plots and the use of fertile soil layers;

· design of water reduction and drainage of the site;

· collection and preparation of initial data provided by the Customer in accordance with the design assignment;

· payment to local government bodies, state supervision and other organizations for work related to the approval of project documentation;

· drawing up technical specifications for design, technical specifications for the supply of equipment to foreign companies and acceptance of design documentation developed by foreign companies.

1.6 Development of the section “Environmental Impact Assessment” (EIA), carried out in accordance with the requirements of current regulatory documents as part of pre-design work, is not taken into account by the prices of the Directory and is determined additionally.

1.7 The base price of design documentation (at the design + working documentation stages) is determined in the manner established by Section II of the “General Guidelines for the Application of Directories of Base Prices for Design Work for Construction”.

1.8 The base price of design documentation for objects, the main indicator of which differs from those given in the table, will be determined by applying the following coefficients:

with an increase in the indicator by 1.5 times - 1.1

over 1.5 to 2 - 1.2

over 2 to 3 - 1.3

over 3 to 4 - 1.4

when the indicator decreases by 1.5 times - 0.9

over 1.5 to 2 - 0.8

over 2 to 3 - 0.75

over 3 to 4 - 0.7

1.9 The distribution of the price of design documentation by design stages is carried out according to the table below and can be specified by agreement between the Contractor and the Customer

Design stage

Percentage of base price

Project(P)

Working documentation

Project documentation

The base price of a detailed design is determined at 90% of the project price.

1.10 The price for developing Justification for investments in construction, carried out in accordance with SP 11-101-95, is determined in the manner established by paragraphs. 2.1 and 2.2 of the Directory, using a coefficient of up to 0.2, and a Petition (Declaration) of intent to invest in the construction of enterprises, buildings and structures - up to 0.15 to the price of developing project documentation.

1.11 Cost of development of design documentation carried out on the basis of initial data, incl. of the basic project developed by foreign companies is determined in accordance with the distribution of the price of project documentation by design stages given in clause 1.9 of the Handbook, with an increasing factor of up to 1.15 depending on the labor intensity of the work.

1.12 The base price of design documentation for reconstruction and technical re-equipment is determined according to the prices of the Directory using a coefficient of up to 2.0, established by the design organization in agreement with the customer in accordance with the labor intensity of the work.

The maximum coefficient can be applied during complete reconstruction or complete technical re-equipment of the facility. When determining the price of reconstruction (technical re-equipment) of only part of a building, structure, or performing certain types of work, an adjustment factor of less than one is applied, in agreement with the customer, taking into account the volume of work compared to new construction.

1.13 Costs associated with performing the functions of a general designer and supervising design work transferred to subcontract are determined in the amount of up to 5% of the price of development of design documentation transferred to subcontracting design organizations, and are paid additionally.

1.14 When developing estimates using the resource method, it is allowed to apply an increasing factor of up to 1.5 to the cost of developing the “Estimate Documentation” section by agreement with the customer. The maximum value of the increasing coefficient when drawing up estimate documentation (using software) is applied if there is no centralized data bank in the region on the cost of resources to take into account the additional costs associated with its formation.

2 BASIC PRICES FOR DEVELOPMENT OF DESIGN DOCUMENTATION

2.1 The base price for the development of design documentation for plants for the production of chemical fibers and threads, as well as production complexes within factories, is determined by summing up the base prices for the design of main production buildings, auxiliary production facilities, incl. Civil emergency, on-site utilities and structures, as well as the development of a master plan related to this project. This base price is determined according to this Directory and other Directories for the design of individual objects. At the same time, the base price for the development of sections “Efficiency of Investments”, “Project of Construction Organization”, “Scientific Organization of Labor” for the object as a whole is taken into account in the total price additionally and amounts to the price of the “project” stage for factories and production complexes within the plant:

· investment efficiency - 15%

· construction organization project - 4%

· scientific organization of labor - 2%

2.2 The cost of development at the “project” stage of the “Environmental Protection” section is determined in addition to 39% of the “project” stage of the plant or production within the plant, determined in the manner provided for in clause 2.1, including:

· protection of atmospheric air - 20%

· protection of the aquatic environment - 10%

· protection of territory and soils - 4%

· solid waste disposal - 5%

2.3 Works and services of the design organization related to:

· production of demonstration materials (except for demonstration models);

· participation together with the Customer in the coordination of finished project documentation with government agencies and local governments;

· protection of the working draft (project) in the exporting and approving authorities

are assessed additionally at 10% of the total cost of developing project documentation.

2.4 If it is necessary to determine the base price of production for enlarged preliminary calculations, the cost of designing newly built production facilities can be determined by applying a coefficient of 1.3 to the base price of design of the main construction projects, and to determine the complex base price of design of a newly built plant - 1.5, taking into account the design auxiliary and service facilities, on-site networks and structures, as well as the general plan and transport.

2.5 In the case where it is planned to carry out construction in queues, the cost of developing projects (working projects) of enterprises is determined at the prices of the Directory based on the main indicators of each queue separately. In this case, up to 20% of the cost of developing the project for all subsequent stages is added to the cost of designing the first stage of construction.

2.6 Table 1 shows basic prices only for individual buildings, workshops and departments of the main production; base prices for auxiliary and general plant facilities and communications, the general plan included in the plant or production are determined additionally according to the relevant chapters of this Directory or, if necessary, according to other Directories.

2.7 Prices of production facilities and facilities (tables 2-4) are given without taking into account transformer substations. The cost of designing transformer substations and switchgears is determined additionally according to Table 5.

2.8 When designing automation to solve problems of information exchange between the lower and upper levels of process control systems or information and measurement systems, the cost of the “Automation” section is determined using a coefficient from 1.2 to 1.4. The size of the coefficient is established by agreement with the customer depending on the number of tasks to be solved for the automation of technological processes, automation of ventilation and air conditioning systems.

2.9 If necessary, in accordance with the design assignment for the development of a process control algorithm (DCS) and emergency protection (EPS) in the “Technological part” section of the project (detailed design, working documentation), as well as in the “Automation of technological processes” section, its cost execution is determined with K = 0.3 from the relevant parts of the project (detailed design, working documentation).

2.10 The base price for designing objects using microprocessor technology is determined with a coefficient of 1.6 to the sections “Automation of technological processes” and “Electrical technical part”.

2.11 The relative cost of sections of design documentation by design stages is indicated in Table 1 in the following sequence:

· working documentation

· working draft

2.12 The distribution of the price determined according to the Directory for the development of documentation for individual types, parts and sections of design work is determined according to the data given in the tables, can be specified by the design organization within the limits of the total cost for each design stage, depending on the complexity of the work, as when performing the work in-house by forces, and when transferring part of the work to subcontracting design organizations in agreement with them.

In the same manner, the relative cost of other types of design work that are not highlighted in the relative cost sections can be determined.

2.13 The relative cost of developing design documentation is given for new construction and does not apply to the cost of developing design documentation for reconstruction and technical re-equipment.

2.14 The cost of drawing up local estimates is taken into account in the relative cost of developing the corresponding sections of the project documentation, except for cases where the cost of performing this work is highlighted in the tables.


» "Handbook of basic prices for design work for construction. Chemical fiber industry facilities (instead of Chapter 5 "Sub-industry of chemical fibers and threads" and Chapter 14 "Ancillary and service facilities, on-site networks and water supply, sewerage, heat supply and electricity structures "" section 9 "Chemical industry" of the Collection of prices for design work for construction. 1987)"

"Handbook of basic prices for design work for construction. Facilities of the chemical fiber industry (instead of Chapter 5 "Sub-industry of chemical fibers and threads" and Chapter 14 "Ancillary and service facilities, on-site networks and water supply, sewerage, heat supply and electricity structures" "section 9 "Chemical industry" of the Collection of prices for design work for construction. 1987)"


FEDERAL CONSTRUCTION AGENCY
AND HOUSING AND COMMUNAL SERVICES

DIRECTORY OF BASIC PRICES FOR DESIGN WORK FOR CONSTRUCTION

CHEMICAL FIBER INDUSTRY FACILITIES

DEVELOPED BY FSUE "CENTRINVESTproject" (Puliko V.I., Turenskaya M.A., Bortnikova E.S.) and JSC "Giproiv" (Yushchenko V.V., Zharova V.R.).

CONSIDERED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia (Stepanov V.A., Grishchenkova T.L.).

INTRODUCED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia.

ADOPTED AND ENTERED INTO EFFECT on May 15, 2004 by letter of the Federal Agency for Construction and Housing and Communal Services dated May 7, 2004 No. AP-2642/10 in agreement with the Department of Industrial and Innovation Policy in the Chemical Industry of the Ministry of Industry, Science and Technology Russian Federation dated April 21, 2002 No. 14-248.

IN REPLACE for Chapter 5 “Sub-industry of chemical fibers and threads” and Chapter 14 “Ancillary and service facilities, on-site networks and structures of water supply, sewerage, heat supply and electricity” of Section 9 “Chemical industry” of the Collection of prices for design work for construction ed. 1987 with changes and additions 1988-1990

1 BASIC POINTS

1.1 The Directory of base prices for design work for construction (hereinafter referred to as the “Directory”) is recommended for determining base prices for the purpose of subsequent formation of contract prices for the development of design documentation for the construction of chemical fiber industry facilities: production facilities, complexes, individual facilities for auxiliary production and auxiliary purposes , special sections of the project.
1.2 Basic prices in the Directory are set depending on the natural indicators of the designed objects: area, productivity, capacity, etc., or for objects as a whole.
1.3 When using this Directory, you should take into account the General instructions for the use of Directories of basic prices for design work for the construction of ed. 2002
1.4 The price level contained in the tables of the Directory is established as of 01/01/2001.
1.5 In addition to the work listed in clause 7 of Section I of the General Guidelines for the use of Directories of basic prices for design work for construction, the basic prices of the Directory do not take into account:
o development of design documentation for individual production of switchboards, cabinets and control panels for electrical systems and automation systems;
o development of technological regulations for the production of products;
o design of energy consumption accounting and control systems;
o design of experimental, pilot-industrial production, workshops, installations, lines;
o design of fire extinguishing systems, fire and security alarms, warning people about a fire;
o technical support of construction;
o development of automated dispatch and control systems for energy supply (ASUE), development of a process control algorithm (PCA) and emergency protection (EPS);
o development of a project for the transportation of large-sized heavy equipment;
o design of a sanitary protection zone;
o development of thermal insulation;
o production and additional sending to the customer of project documentation on electronic media (floppy disks, CDs, etc.):
o development of a three-dimensional electronic model of pipelines and equipment, ventilation systems, instrumentation and electrical cables, load-bearing building structures;
o development of industrial television projects;
o development of the “Declaration of Industrial Safety” and examination of the “Declaration of Industrial Safety”;
o development of measures for the restoration (reclamation) of land plots and the use of fertile soil layers;
o design of water reduction and drainage of the site;
o collection and preparation of initial data provided by the Customer in accordance with the design assignment;
o payment to local government bodies, state supervision and other organizations for work related to the approval of project documentation;
o drawing up technical specifications for design, technical specifications for the supply of equipment to foreign companies and acceptance of design documentation developed by foreign companies.
1.6 Development of the section “Environmental Impact Assessment” (EIA), carried out in accordance with the requirements of current regulatory documents as part of pre-design work, is not taken into account by the prices of the Directory and is determined additionally.
1.7 The base price of design documentation (at the design + working documentation stages) is determined in the manner established by Section II of the “General Guidelines for the Application of Directories of Base Prices for Design Work for Construction”.
1.8 The base price of design documentation for objects, the main indicator of which differs from those given in the table, will be determined by applying the following coefficients:
with an increase of 1.5 times -1.1
over 1.5 to 2 -1.2
over 2 to 3 -1.3
over 3 to 4 -1.4
when the indicator decreases by 1.5 times -0.9
over 1.5 to 2 -0.8
over 2 to 3 -0.75
over 3 to 4 -0.7
1.9 The distribution of the price of design documentation by design stages is carried out according to the table below and can be specified by agreement between the Contractor and the Customer

Russian Federation

"DIRECTORY OF BASIC PRICES FOR DESIGN WORK FOR CONSTRUCTION. CHEMICAL FIBER INDUSTRY FACILITIES" (approved by Letter of Rosstroi dated 05/07/2004 N AP-2642/10)

Adopted by letter of the Federal Agency for Construction and Housing and Communal Services dated May 7, 2004 N AP-2642/10.

In place of Chapter 5 "Sub-industry of chemical fibers and threads" and Chapter 14 "Ancillary and service facilities, on-site networks and structures of water supply, sewerage, heat supply and electricity" of Section 9 "Chemical industry" of the Collection of prices for design work for construction ed. 1987 with changes and additions 1988-1990

1.1 The Directory of base prices for design work for construction (hereinafter referred to as the “Directory”) is recommended for determining base prices for the purpose of subsequent formation of contract prices for the development of design documentation for the construction of chemical fiber industry facilities: production facilities, complexes, individual facilities for auxiliary production and auxiliary purposes , special sections of the project.

1.2 Basic prices in the Directory are set depending on the natural indicators of the designed objects: area, productivity, capacity, etc., or for objects as a whole.

1.3 When using this Directory, you should take into account the General instructions for the use of Directories of basic prices for design work for the construction of ed. 2002

1.4 The price level contained in the tables of the Directory is established as of 01/01/2001.

1.5 In addition to the work listed in clause 7 of Section I of the General Guidelines for the use of Directories of basic prices for design work for construction, the basic prices of the Directory do not take into account:

Development of design documentation for individual production of switchboards, cabinets and control panels for electrical systems and automation systems;

Development of technological regulations for the production of products;

Design of energy consumption accounting and control systems;

Design of experimental, pilot-industrial production, workshops, installations, lines;

Design of fire extinguishing systems, fire and security alarms, warning people about a fire;

Technical support of construction;

Development of automated dispatch and control systems for energy supply (ASUE), development of a process control algorithm (DCS) and emergency protection (EPS);

Development of a project for the transportation of large-sized heavy equipment;

Design of a sanitary protection zone;

Development of thermal insulation;

Production and additional sending to the customer of project documentation on electronic media (floppy disks, CDs, etc.):

Development of a three-dimensional electronic model of pipelines and equipment, ventilation systems, instrumentation and electrical cables, load-bearing building structures;

Development of industrial television projects;

Development of the "Declaration of Industrial Safety" and examination of the "Declaration of Industrial Safety";

Development of measures for the restoration (reclamation) of land plots and the use of fertile soil layers;

Design of water reduction and drainage of the site;

Collection and preparation of initial data provided by the Customer in accordance with the design assignment;

Payment to local government bodies, state supervision and other organizations for work related to the approval of project documentation;

Drawing up technical specifications for design, technical specifications for the supply of equipment to foreign companies and acceptance of design documentation developed by foreign companies.

1.6 Development of the section “Environmental Impact Assessment” (EIA), carried out in accordance with the requirements of current regulatory documents as part of pre-design work, is not taken into account by the prices of the Directory and is determined additionally.

1.9 The distribution of the price of design documentation by design stages is carried out according to the table below and can be specified by agreement between the Contractor and the Customer

Design stagePercentage of base price
Project (P)30
Working documentation70
Project documentation100

The base price of a detailed design is determined at 90% of the project price.

1.10 The price for developing Justification for investments in construction, carried out in accordance with SP 11-101-95, is determined in the manner established by paragraphs. 2.1 and 2.2 of the Directory, using a coefficient of up to 0.2, and a Petition (Declaration) of intent to invest in the construction of enterprises, buildings and structures - up to 0.15 to the price of developing project documentation.

1.11 Cost of development of design documentation carried out on the basis of initial data, incl. of the basic project developed by foreign companies is determined in accordance with the distribution of the price of project documentation by design stages given in clause 1.9 of the Handbook, with an increasing factor of up to 1.15 depending on the labor intensity of the work.

1.12 The base price of design documentation for reconstruction and technical re-equipment is determined according to the prices of the Directory using a coefficient of up to 2.0, established by the design organization in agreement with the customer in accordance with the labor intensity of the work.

The maximum coefficient can be applied during complete reconstruction or complete technical re-equipment of the facility. When determining the price of reconstruction (technical re-equipment) of only part of a building, structure, or performing certain types of work, an adjustment factor of less than one is applied, in agreement with the customer, taking into account the volume of work compared to new construction.

1.13 Costs associated with performing the functions of a general designer and supervising design work transferred to subcontract are determined in the amount of up to 5% of the price of development of design documentation transferred to subcontracting design organizations, and are paid additionally.

1.14 When developing estimates using the resource method, it is allowed to apply an increasing factor of up to 1.5 to the cost of developing the “Estimate Documentation” section by agreement with the customer. The maximum value of the increasing coefficient when drawing up estimate documentation (using software) is applied if there is no centralized data bank in the region on the cost of resources to take into account the additional costs associated with its formation.

2.1 The base price for the development of design documentation for plants for the production of chemical fibers and threads, as well as production complexes within factories, is determined by summing up the base prices for the design of main production buildings, auxiliary production facilities, incl. Civil emergency, on-site utilities and structures, as well as the development of a master plan related to this project. This base price is determined according to this Directory and other Directories for the design of individual objects. At the same time, the base price for the development of sections “Efficiency of Investments”, “Project of Construction Organization”, “Scientific Organization of Labor” for the object as a whole is taken into account in the total price additionally and amounts to the price of the “project” stage for factories and production complexes within the plant:

Investment efficiency -15%

Construction organization project - 4%

Scientific organization of labor - 2%

2.2 The cost of development at the “project” stage of the “Environmental Protection” section is determined in addition to 39% of the “project” stage of the plant or production within the plant, determined in the manner provided for in clause 2.1, including:

Air protection - 20%

Protection of the aquatic environment - 10%

Protection of territory and soils - 4%

Solid waste disposal - 5%

2.3 Works and services of the design organization related to:

Production of demonstration materials (except for demonstration models);

Participation, together with the Customer, in the coordination of finished project documentation with government agencies and local governments;

Protection of the working draft (project) in the examining and approving authorities

are assessed additionally at 10% of the total cost of developing project documentation.

2.4 If it is necessary to determine the base price of production for enlarged preliminary calculations, the cost of designing newly built production facilities can be determined by applying a coefficient of 1.3 to the base price of design of the main construction projects, and to determine the complex base price of design of a newly built plant - 1.5, taking into account the design auxiliary and service facilities, on-site networks and structures, as well as the general plan and transport.

2.5 In the case where it is planned to carry out construction in queues, the cost of developing projects (working projects) of enterprises is determined at the prices of the Directory based on the main indicators of each queue separately. In this case, up to 20% of the cost of developing the project for all subsequent stages is added to the cost of designing the first stage of construction.

2.6 Table 1 shows basic prices only for individual buildings, workshops and departments of the main production; base prices for auxiliary and general plant facilities and communications, the general plan included in the plant or production are determined additionally according to the relevant chapters of this Directory or, if necessary, according to other Directories.

2.7 Prices of production facilities and facilities (Tables 2-4) are given without taking into account transformer substations. The cost of designing transformer substations and switchgears is determined additionally according to Table 5.

2.8 When designing automation to solve problems of information exchange between the lower and upper levels of automated process control systems or information and measurement systems, the cost of the “Automation” section is determined using a coefficient from 1.2 to 1.4. The size of the coefficient is established by agreement with the customer depending on the number of tasks to be solved for the automation of technological processes, automation of ventilation and air conditioning systems.

2.9 If necessary, in accordance with the design assignment for the development of a process control algorithm (DCS) and emergency protection (EPS) in the “Technological part” section of the project (detailed design, working documentation), as well as in the “Automation of technological processes” section, its cost execution is determined with K=0.3 from the relevant parts of the project (detailed design, working documentation).

2.10 The base price for designing objects using microprocessor technology is determined with a coefficient of 1.6 to the sections “Automation of technological processes” and “Electrical technical part”.

2.11 The relative cost of sections of design documentation by design stages is indicated in Table 1 in the following sequence:

Working documentation

Working draft

2.12 The distribution of the price determined according to the Directory for the development of documentation for individual types, parts and sections of design work is determined according to the data given in the tables, can be specified by the design organization within the limits of the total cost for each design stage, depending on the complexity of the work, as when performing the work in-house by forces, and when transferring part of the work to subcontracting design organizations in agreement with them.

In the same manner, the relative cost of other types of design work that are not highlighted in the relative cost sections can be determined.

2.13 The relative cost of developing design documentation is given for new construction and does not apply to the cost of developing design documentation for reconstruction and technical re-equipment.

2.14 The cost of drawing up local estimates is taken into account in the relative cost of developing the corresponding sections of the project documentation, except for cases where the cost of performing this work is highlighted in the tables.

---

FEDERAL CONSTRUCTION AGENCY
AND HOUSING AND COMMUNAL SERVICES

BASIC PRICE GUIDE
FOR DESIGN WORK FOR CONSTRUCTION

OBJECTS INDUSTRY
CHEMICAL FIBER

MOSCOW 2004

Directory of basic prices for design work for construction “Chemical fiber industry facilities” 2004

DEVELOPED BY FSUE "CENTRINVESTproject" (Puliko V.I., Turenskaya M.A., Bortnikova E.S.) and JSC "Giproiv" (Yushchenko V.V., Zharova V.R.).

CONSIDERED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia (Stepanov V.A., Grishchenkova T.L.).

INTRODUCED by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia.

ADOPTED AND ENTERED INTO EFFECTMay 15, 2004 by letter of the Federal Agency for Construction and Housing and Communal Services dated May 7, 2004 No. AP-2642/10 in agreement with the Department of Industrial and Innovation Policy in the Chemical Industry of the Ministry of Industry, Science and Technology of the Russian Federation dated April 21, 2002 No. 14-248.

IN REPLACEMENT OF THE CHAPTER 5 “Sub-industry of chemical fibers and threads” and Chapter 14 “Ancillary and service facilities, on-site networks and structures of water supply, sewerage, heat supply and electricity” of Section 9 “Chemical industry” of the Collection of prices for design work for construction ed. 1987 with amendments and additions 1988 - 1990

Explanations and consultations on the application of this Handbook are provided by FSUE "CENTRINVESTproject" (125057 , G. Moscow, Leningradsky etc., 63 , tel. (095 ) 157 - 39 - 42 ) and JSC "Giproiv" ( 141009 , G. Mytishchi Moscow region., st. Carla Marx, 4 , tel. (095 ) (583 - 33 - 81 ).

1 BASIC POINTS

1.1 The Directory of base prices for design work for construction (hereinafter referred to as the “Directory”) is recommended for determining base prices for the purpose of subsequent formation of contract prices for the development of design documentation for the construction of chemical fiber industry facilities: production facilities, complexes, individual facilities for auxiliary production and auxiliary purposes , special sections of the project.

1.2 Basic prices in the Directory are set depending on the natural indicators of the designed objects: area, productivity, capacity, etc., or for objects as a whole.

1.3 When using this Directory, you should take into account the General instructions for the use of Directories of basic prices for design work for the construction of ed. 2002

1.4 The price level contained in the tables of the Directory is established as of 01/01/2001.

1.5 In addition to the work listed in paragraph 7 of section I General guidelines for the use of Directories of base prices for design work for construction; the base prices of the Directory do not take into account:

· development of design documentation for individual production of switchboards, cabinets and control panels for electrical systems and automation systems;

· development of technological regulations for the production of products;

· design of energy consumption accounting and control systems;

· design of experimental, pilot-industrial production, workshops, installations, lines;

· design of fire extinguishing systems, fire and security alarms, warning people about a fire;

· technical support of construction;

· development of automated dispatch and control systems for energy supply (ASUE), development of a process control algorithm (PCA) and emergency protection (EPS);

· development of a project for transporting large-sized heavy equipment;

· design of a sanitary protection zone;

· development of thermal insulation;

· production and additional sending to the customer of design documentation on electronic media (floppy disks, CD, etc.):

· development of a three-dimensional electronic model of a pipelineov and equipment, ventilation systems, wiring of instrumentation and automation routes and electrical cables, load-bearing building structures;

· development of industrial television projects;

· development of the “Declaration of Industrial Safety” and examination of the “Declaration of Industrial Safety”;

· development of measures for the restoration (reclamation) of land plots and the use of fertile soil layers;

· waterpony designsite drainage and drainage;

· collection and preparation of initial data provided by the Customer in accordance with the design assignment;

· payment to local government bodies, state supervision and other organizations for work related to the approval of project documentation;

· drawing up technical specifications for design, technical specifications for the supply of equipment to foreign companies and acceptance of design documentation developed by foreign companies.

1.6 Development of the section “Environmental Impact Assessment” (EIA), carried out in accordance with the requirements of current regulatory documents as part of pre-design work, is not taken into account by the prices of the Directory and is determined additionally.

1.7 The base price of project documentation (at the design + working documentation stages) is determined in the manner established by section II “General guidelines for the use of Directories of basic prices for design work for construction.”

1.8 The base price of design documentation for objects, the main indicator of which differs from those given in the table, will be determined by applying the following coefficients:

with an increase in 1.5 times - 1.1

Over 1.5 to 2 - 1.2

Over 2 to 3 - 1.3

Over 3 to 4 - 1.4

when the indicator decreases by 1.5 times - 0.9

Over 1.5 to 2 - 0.8

Over 2 to 3 - 0.75

Over 3 to 4 - 0.7

Design stage

Percentage of base price

Project (P)

Working documentation

Project documentation

The base price of a working project is determined in the amount90% of the project price.

1.10 The price for developing Justification for investments in construction, carried out in accordance with SP 11-101-95, is determined in the manner established by paragraphs. and the Directory, using a coefficient of up to 0.2, and a Petition (Declaration) of intent to invest in the construction of enterprises, buildings and structures - up to 0.15 to the price of developing project documentation.

1.11 Cost of development of design documentation carried out on the basis of initial data, incl. of the basic project developed by foreign companies is determined in accordance with the distribution of the price of design documentation by design stages given in paragraph of the Directory, with an increasing factor of up to 1.15 depending on the complexity of the work.

1.12 The base price of design documentation for reconstruction and technical re-equipment is determined according to the prices of the Directory using a coefficient of up to 2.0, established by the design organization in agreement with the customer in accordance with the labor intensity of the work.

The maximum coefficient can be applied during complete reconstruction or complete technical re-equipment of the facility. When determining the price of reconstruction (technical re-equipment) of only part of a building, structure, or performing certain types of work, an adjustment factor of less than one is applied, in agreement with the customer, taking into account the volume of work compared to new construction.

1.13 Costs associated with performing the functions of a general designer and supervising design work transferred to subcontract are determined in the amount of up to 5% of the price of development of design documentation transferred to subcontracting design organizations, and are paid additionally.

1.14 When developing estimates using the resource method, it is allowed to apply an increasing factor of up to 1.5 to the cost of developing the “Estimate Documentation” section by agreement with the customer. The maximum value of the increasing coefficient when drawing up estimate documentation (using software) is applied if there is no centralized data bank in the region on the cost of resources to take into account the additional costs associated with its formation.

2 BASIC PRICES FOR DEVELOPMENT OF DESIGN DOCUMENTATION

· investment efficiency - 15%

· construction organization project - 4%

· scientific organization of labor - 2%

2.8 When designing automation to solve problems of information exchange between the lower and upper levels of process control systems or information and measurement systems, the cost of the “Automation” section is determined using a coefficient from 1.2 to 1.4. The size of the coefficient is established by agreement with the customer depending on the number of tasks to be solved for the automation of technological processes, automation of ventilation and air conditioning systems.

2.9 If necessary, in accordance with the design assignment for the development of a process control algorithm (DCS) and emergency protection (EPS) in the “Technological part” section of the project (detailed design, working documentation), as well as in the “Automation of technological processes” section, its cost execution is determined with K = 0.3 from the relevant parts of the project (detailed design, working documentation).

2.10 The base price for designing objects using microprocessor technology is determined with a coefficient of 1.6 to the sections “Automation of technological processes” and “Electrical technical part”.

2.11 The relative cost of sections of design documentation by design stages is indicated in the table in the following sequence:

· project

· working documentation

· working draft

2.12 The distribution of the price determined according to the Directory for the development of documentation for individual types, parts and sections of design work is determined according to the data given in the tables, can be specified by the design organization within the limits of the total cost for each design stage, depending on the complexity of the work, as when performing the work in-house by forces, and when transferring part of the work to subcontracting design organizations in agreement with them.

In the same manner, the relative cost of other types of design work that are not highlighted in the relative cost sections can be determined.

2.13 The relative cost of developing design documentation is given for new construction and does not apply to the cost of developing design documentation for reconstruction and technical re-equipment.

2.14 The cost of drawing up local estimates is taken into account in the relative cost of developing the corresponding sections of the project documentation, except for cases where the cost of performing this work is highlighted in the tables.

Accepted and put into effect

By letter from Rosstroy

FEDERAL CONSTRUCTION AGENCY

AND HOUSING AND COMMUNAL SERVICES

DIRECTORY OF BASIC PRICES FOR DESIGN WORK FOR CONSTRUCTION

CHEMICAL FIBER INDUSTRY FACILITIES

Developed by FSUE "CENTRINVESTproject" (Puliko V.I., Turenskaya M.A., Bortnikova E.S.) and OJSC "Giproiv" (Yushchenko V.V., Zharova V.R.).

Reviewed by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia (Stepanov V.A., Grishchenkova T.L.)

Introduced by the Department of Pricing and Estimated Standardization of the Gosstroy of Russia

Adopted and put into effect on May 15, 2004 by Letter of the Federal Agency for Construction and Housing and Communal Services dated May 7, 2004 N AP-2642/10 in agreement with the Department of Industrial and Innovation Policy in the Chemical Industry, Science and Technology of the Russian Federation dated April 21, 2002 N 14-248.

In place of Chapter 5 "Sub-industry of chemical fibers and threads" and Chapter 14 "Objects for auxiliary and service purposes, on-site networks with water supply, sewerage, heat supply and electricity structures" Section 9 "Chemical industry" Collection of prices for design work for construction ed. 1987 with changes and additions 1988 - 1990

1. BASIC PROVISIONS

1.1. The Directory of base prices for design work for construction (hereinafter referred to as the "Directory") is recommended for determining base prices for the purpose of subsequent formation of contract prices for the development of design documentation for the construction of chemical fiber industry facilities: production facilities, complexes, individual facilities for auxiliary production and auxiliary purposes, special sections of the project.

1.2. Basic prices in the Directory are set depending on the natural indicators of the designed objects: area, productivity, capacity, etc., or for objects as a whole.

1.3. When using this Directory, you should take into account the General guidelines for the use of Directories of basic prices for design work for the construction of ed. 2002

1.4. The price level contained in the tables of the Directory is established as of 01/01/2001.

1.5. In addition to the work listed in clause 7 of Section I of the General Guidelines for the Application of Directories of Basic Prices for Design Work for Construction, the Basic Prices of the Directory do not take into account:

Development of design documentation for individual production of switchboards, cabinets and control panels for electrical systems and automation systems;

Development of technological regulations for the production of products;

Design of energy consumption accounting and control systems;

Design of experimental, pilot-industrial production, workshops, installations, lines;

Design of fire extinguishing systems, fire and security alarms, warning people about a fire;

Technical support of construction;

Development of automated dispatch and control systems for energy supply (ASUE), development of a process control algorithm (DCS) and emergency protection (EPS);

Development of a project for the transportation of large-sized heavy equipment;

Design of a sanitary protection zone;

Development of thermal insulation;

Production and additional sending to the customer of project documentation on electronic media (floppy disks, CDs, etc.);

Development of a three-dimensional electronic model of pipelines and equipment, ventilation systems, instrumentation and electrical cables, load-bearing building structures;

Development of industrial television projects;

Development of the "Declaration of Industrial Safety" and examination of the "Declaration of Industrial Safety";

Development of measures for the restoration (reclamation) of land plots and the use of fertile soil layers;

Design of water reduction and drainage of the site;

Collection and preparation of initial data provided by the Customer in accordance with the design assignment;

Payment to local government bodies, state supervision and other organizations for work related to the approval of project documentation;

Drawing up technical specifications for design, technical specifications for the supply of equipment to foreign companies and acceptance of design documentation developed by foreign companies.

1.6. The development of the section “Environmental Impact Assessment” (EIA), carried out in accordance with the requirements of current regulatory documents as part of pre-design work, is not taken into account by the prices of the Directory and is determined additionally.

1.7. The base price of design documentation (at the design + working documentation stages) is determined in the manner established by Section II of the “General Guidelines for the Application of Directories of Base Prices for Design Work for Construction”.

1.8. The base price of project documentation for objects, the main indicator of which differs from those given in the table, will be determined by applying the following coefficients:

with an increase in the indicator by 1.5 times - 1.1

over 1.5 to 2- 1.2

over 2 to 3- 1.3

over 3 to 4- 1.4

when the indicator decreases by 1.5 times - 0.9

over 1.5 to 2- 0.8

over 2 to 3- 0.75

over 3 to 4- 0.7

1.9. The distribution of the price of design documentation by design stages is carried out according to the table below and can be specified by agreement between the Contractor and the Customer.

Design stage

Percentage of base price

Project (P)

Working documentation

Project documentation

The base price of a detailed design is determined at 90% of the project price.

1.10. The price for developing Justification for investments in construction carried out in accordance with SP 11-101-95 is determined in the manner established by paragraphs. 2.1 and 2.2 of the Directory, using a coefficient of up to 0.2, and a Petition (Declaration) of intent to invest in the construction of enterprises, buildings and structures - up to 0.15 to the price of developing project documentation.

1.11. The cost of developing design documentation carried out on the basis of initial data, incl. of the basic project developed by foreign companies is determined in accordance with the distribution of the price of project documentation by design stages given in clause 1.9 of the Handbook, with an increasing factor of up to 1.15 depending on the labor intensity of the work.

1.12. The base price of design documentation for reconstruction and technical re-equipment is determined according to the prices of the Directory using a coefficient of up to 2.0, established by the design organization in agreement with the customer in accordance with the labor intensity of the work.

The maximum coefficient can be applied during complete reconstruction or complete technical re-equipment of the facility. When determining the price of reconstruction (technical re-equipment) of only part of a building, structure, or performing certain types of work, an adjustment factor of less than one is applied, in agreement with the customer, taking into account the volume of work compared to new construction.

1.13. Costs associated with performing the functions of a general designer and supervising design work transferred to subcontract are determined in the amount of up to 5% of the price of development of design documentation transferred to subcontracting design organizations, and are paid additionally.

1.14. When developing estimates using the resource method, it is allowed to apply an increasing factor of up to 1.5 to the cost of developing the “Estimate Documentation” section by agreement with the customer. The maximum value of the increasing coefficient when drawing up estimate documentation (using software) is applied if there is no centralized data bank in the region on the cost of resources to take into account the additional costs associated with its formation.

2. BASIC PRICES FOR DEVELOPMENT OF DESIGN DOCUMENTATION

2.1. The base price for the development of design documentation for plants for the production of chemical fibers and threads, as well as production complexes within the plants, is determined by summing up the base prices for the design of main production buildings, auxiliary production facilities, incl. Civil emergency, on-site utilities and structures, as well as the development of a master plan related to this project. This base price is determined according to this Directory and other Directories for the design of individual objects. At the same time, the base price for the development of sections “Efficiency of Investments”, “Project of Construction Organization”, “Scientific Organization of Labor” for the object as a whole is taken into account in the total price additionally and amounts to the price of the “project” stage for factories and production complexes within the plant:

Investment efficiency - 15%

Construction organization project - 4%

Scientific organization of labor - 2%

2.2. The cost of development at the “project” stage of the “Environmental Protection” section is determined in addition to 39% of the “project” stage of the plant or production within the plant, determined in the manner provided for in clause 2.1, including:

Atmospheric air protection - 20%

Protection of the aquatic environment - 10%

Protection of territory and soils - 4%

Solid waste disposal - 5%

2.3. Works and services of the design organization related to:

Production of demonstration materials (except for demonstration models);

Participation, together with the Customer, in the coordination of finished project documentation with government agencies and local governments;

Protection of the working draft (project) in the examining and approving authorities

are assessed additionally at 10% of the total cost of developing project documentation.

2.4. If it is necessary to determine the base price of production for enlarged preliminary calculations, the cost of designing newly built production facilities can be determined by applying a coefficient of 1.3 to the base price of designing the main construction projects, and to determine the complex base price of designing a newly built plant - 1.5, taking into account the design of facilities auxiliary and service purposes, on-site networks and structures, as well as the general plan and transport.

2.5. In the case where it is planned to carry out construction in queues, the cost of developing projects (working projects) of enterprises is determined at the prices of the Directory based on the main indicators of each queue separately. In this case, up to 20% of the cost of developing the project for all subsequent stages is added to the cost of designing the first stage of construction.

2.6. Table 1 shows basic prices only for individual buildings, workshops and departments of the main production; base prices for auxiliary and general plant facilities and communications, the general plan included in the plant or production are determined additionally according to the relevant chapters of this Directory or, if necessary, according to other Directories.

2.7. Prices for production facilities and facilities (Tables 2 - 4) are given without taking into account transformer substations. The cost of designing transformer substations and switchgears is determined additionally according to Table 5.

2.8. When designing automation to solve problems of information exchange between the lower and upper levels of automated process control systems or information and measurement systems, the cost of the “Automation” section is determined using a coefficient from 1.2 to 1.4. The size of the coefficient is established by agreement with the customer depending on the number of tasks to be solved for the automation of technological processes, automation of ventilation and air conditioning systems.

2.9. If necessary, in accordance with the design assignment for the development of a process control algorithm (DCS) and emergency protection (EPS) in the “Technological part” section of the project (detailed design, working documentation), as well as in the “Automation of technological processes” section, the cost of its implementation determined with K = 0.3 from the relevant parts of the project (detailed design, working documentation).

2.10. The base price for designing objects using microprocessor technology is determined with a coefficient of 1.6 to the sections “Automation of technological processes” and “Electrical engineering”.

2.11. The relative costs of sections of design documentation by design stages are indicated in Table 1 in the following sequence:

Project

Working documentation

Working draft

2.12. The distribution of the price determined according to the Directory for the development of documentation for individual types, parts and sections of design work is determined according to the data given in the tables; it can be specified by the design organization within the limits of the total cost for each design stage, depending on the labor intensity of the work, as when performing the work on its own. , and when transferring part of the work to subcontracting design organizations in agreement with them.

In the same manner, the relative cost of other types of design work that are not highlighted in the relative cost sections can be determined.

2.13. The relative cost of developing design documentation is given for new construction and does not apply to the cost of developing design documentation for reconstruction and technical re-equipment.

2.14. The cost of drawing up local estimates is taken into account in the relative cost of developing the corresponding sections of the project documentation, with the exception of cases where the cost of performing this work is highlighted in the tables.

Chapter 1. Main and auxiliary objects

and general plant purposes

Share