Operational quality control of construction and installation works. Download operational quality control schemes for construction, repair and installation works. Map of operational control of brickwork walls

Description:

Status: active

Russian name: Cards of operational quality control of main construction and installation works

Date of introduction: 1999-01-01

Designed in: OJSC PKTIpromstroy 125040, Moscow, Leningradsky Prospekt, 26

Approved in: OJSC PKTIpromstroy (01/01/1999)

Area and conditions of application: Operational control must be carried out in strict accordance with the enterprise standard (STP) “Regulations on operational quality control”. The main documents of operational quality control are operational control cards. They must be constantly kept at the construction site by the construction manager and presented at the request of persons monitoring the quality of work. They indicate the responsibilities of officials when exercising operational control. If work at the site is headed by one manager (foreman, foreman), then he performs all control functions specified in the operational control cards.
Operational quality control cards are intended for line engineering and technical workers and foremen, and can also be used by persons exercising construction quality control.

Table of contents: 1. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE COLUMNS
2. OPERATIONAL CONTROL CARD FOR INSTALLATION OF LARGE BLOCK STRIP FOUNDATIONS
3. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS
4. OPERATIONAL CONTROL CARD WHEN INSTALLING BEANS
5. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS
6. OPERATIONAL CONTROL CARD FOR INSTALLATION OF FLOOR PANELS (COATING)
7. OPERATIONAL CONTROL CHART FOR INSTALLING WALL FORMWORK
8. OPERATIONAL CONTROL CARD FOR INSTALLATION OF FORMWORK FOR COLUMNS AND SLOBS
9. OPERATIONAL CONTROL CHART WHEN INSTALLING FOUNDATION FORMWORK
10. KAPTA OF OPERATIONAL CONTROL OF STRUCTURE REINFORCEMENT
11. OPERATIONAL CONTROL CHART FOR CONCRETE PLOCKING
12. OPERATIONAL CONTROL CARD FOR WALL CONCRETE PASTING
13. OPERATIONAL CONTROL CHART FOR COLUMNS CONCRETE PATING
14. OPERATIONAL CONTROL CHART FOR BRICK PILLARS
15. OPERATIONAL CONTROL CHART FOR WALL BRICK MASONRY
16. OPERATIONAL CONTROL CARD FOR INSTALLATION OF WINDOW AND DOOR UNITS

Text of the document Maps of operational quality control of main construction and installation works












11.9.1 During the execution of production processes and operations, operational control in order to identify defects that may be hidden when the process or operation continues, and to take measures to prevent and eliminate these defects.

11.9.2 With operational control, the person carrying out construction checks:

Compliance of the sequence and composition of the technological operations performed with the technological and regulatory documentation applicable to these technological operations;

Compliance with the technological regimes established technological maps and regulations;

Compliance of quality indicators of operations and their results with the requirements of design and technological documentation, as well as regulatory documentation applicable to these technological operations.

11.9.2 During the construction process, an assessment of the work performed, the results of which affect safety, must be carried out object, but in accordance with the adopted technology become unavailable for control after the start of subsequent work, as well as completed building structures and plots utility networks, the elimination of defects identified by inspection is impossible without dismantling or damaging subsequent structures and sections of utility networks. Representatives of the relevant state supervision bodies, designer’s supervision, as well as, if necessary, independent experts may participate in these control procedures. The contractor notifies the other participants of the timing of these procedures no later than three working days in advance.

11.9.3 The results of acceptance of work hidden by subsequent work, in accordance with the requirements of design and regulatory documentation, are documented in certificates of inspection of hidden work ( Appendix M ). The developer (customer) may require a re-inspection after eliminating the identified defects.

11.9.4 To the procedure for assessing the conformity of individual structures, tiers of structures (floors), the work performer must submit inspection reports of all hidden works included in these structures, geodetic as-built diagrams, as well as test reports for structures in cases provided for in the design documentation and (or) construction contract. The developer (customer) can check the accuracy of the as-built geodetic schemes presented by the contractor. For this purpose, the performer of the work must preserve the alignment axes and installation guidelines fixed in kind until the completion of acceptance.

The results of acceptance of individual structures must be documented in acceptance certificates for critical structures ( Appendix N ).

11.9.5 Tests of sections of utility networks and installed utility equipment are carried out in accordance with the requirements of the relevant regulatory documents and are documented in acceptance certificates for critical structures (Appendix H).

11.9.6 If defects in work, structures, or sections of utility networks are discovered as a result of stage-by-stage acceptance, the corresponding acts must be drawn up only after the identified defects have been eliminated.

In cases where subsequent work must begin after a break of more than 6 months from the completion of phased acceptance, before resuming work, these procedures should be repeated with the execution of the relevant acts.

11.9.7 Places for performing control operations, their frequency, performers, methods and measuring instruments, forms for recording results, the procedure for making decisions when identifying non-compliance with established requirements must comply with the requirements of design, technological and regulatory documentation.

11.9.8 The person carrying out the construction appoints with his administrative documents the responsible executors for performing operational control, documenting its results and eliminating defects identified by the control.

The results of operational control must be documented in special work logs.

Technological control consists of checking the compliance of characteristics, modes and other indicators technological process established requirements. A type of technological control is operational control. At operational control product quality checks compliance with specific regulatory requirements, implemented during the execution of the next technological operation. Its purpose is to detect and eliminate defects in the process of manufacturing products or constructing buildings and structures. The executor of operational control is production personnel (workers, foremen, foremen). This type of control is considered as labor quality control.

During operational control the following is checked:

Hidden parameters of the product, control of which is subsequently impossible or difficult (reinforcement cages, etc.);

Compliance with the technology for performing construction processes specified in work projects;

Compliance of the work performed with the working drawings, building regulations and work rules and standards;

Stability of parameters of products included in the finished product control range;

Product parameters depending on quality and condition technological equipment and technological process (thickness of the protective layer of concrete, location of embedded parts, curvature and non-straightness of the surface).

Operational control is carried out according to special operational quality control schemes (OSQC) for all construction and installation processes, attached to technological maps or labor process maps. SOKK is a project document that defines the performers, composition, method and time of quality control of construction processes for operations. It is developed based on the requirements of regulatory documents and state standards. It lists specific operations and indicates the requirements of the standard (or building codes) that are observed when performing this operation, and also provides a description of the tool with which operational control is carried out. The card also indicates who specifically exercises control (worker, foreman, foreman, department technical control etc.).

Operational control should be carried out after the completion of production operations or construction processes and ensure the timely identification of defects and the causes of their occurrence, as well as

timely adoption of measures to eliminate and prevent them.

Operational control should be carried out by work producers and foremen, and self-control - by work performers. Construction laboratories and geodetic services should also be involved in operational control. The main working documents for operational quality control should be operational control schemes developed as part of work projects.

The operational control scheme must contain:

  1. design sketches indicating permissible deviations in dimensions and required measurement accuracy, as well as information on the required quality characteristics of materials;
  2. a list of operations or processes, the quality of which must be checked by the work performer (foreman);
  3. a list of operations or processes controlled with the participation of the construction laboratory and geodetic service;
  4. a list of hidden works that are subject to inspection and the drawing up of a report;
  5. requirements of building codes and regulations, and in necessary cases– main characteristics of the quality of the material (structure);
  6. data on the composition of the control established on the basis of the requirements of regulatory documents and working drawings, indicating what needs to be checked;
  7. instructions on the method of monitoring performed operations;
  8. timing of control.

Operational control is entrusted to foremen and foremen, and its organization is entrusted to chief engineers of construction and installation organizations.

7. Acceptance control.

Acceptance control finished products are carried out at the final stage of the technological process. The number of parameters checked must meet the requirements of standards and building codes. Internal inspection control is carried out according to a schedule approved by the management of the enterprise, usually at least once a quarter. Acceptance control should be carried out to check and assess the quality of completed construction of enterprises, buildings and structures or their parts, as well as hidden work and individual critical structures. All hidden work is subject to acceptance with the drawing up of inspection reports. An inspection report for hidden work must be drawn up for a completed process carried out by an independent department of performers. Drawing up inspection reports for hidden work in cases where subsequent work must begin after a long break should be carried out immediately before subsequent work is carried out. Individual critical structures, as they are ready, are subject to acceptance during the construction process with the preparation of an interim acceptance certificate for these structures. The list of critical structures subject to intermediate acceptance is established by the project.

In addition to production control in construction and installation organizations (input, operational, acceptance) the quality of construction is monitored by state and departmental control and supervision bodies, acting on the basis of special provisions on them (fire, sanitary, mining, etc.). Construction organizations must develop organizational, technical and economic measures aimed at ensuring construction quality control. These activities should, in parity, include the creation of construction laboratories, geodetic services, advanced training and skill of performers. At all stages of construction, in order to check the effectiveness of previously performed production controls, selectively carry out inspection control. It is carried out by special services, if they are part of the construction organization, or by commissions specially created for this purpose. According to the results production and inspection quality control Construction and installation work develops measures to eliminate identified defects, taking into account the requirements of designer supervision of design organizations and state supervisory authorities.

Design, Engineering and Technological Institute of Industrial Construction

OJSC PKTIpromstroy

OPERATIONAL QUALITY CONTROL CARDS FOR MAIN CONSTRUCTION AND INSTALLATION WORKS

1. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE COLUMNS

2. OPERATIONAL CONTROL CARD FOR INSTALLATION OF LARGE BLOCK STRIP FOUNDATIONS

3. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS

4. OPERATIONAL CONTROL CARD WHEN INSTALLING BEANS

5. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS

6. OPERATIONAL CONTROL CARD FOR INSTALLATION OF FLOOR PANELS (COATING)

7. OPERATIONAL CONTROL CHART FOR INSTALLING WALL FORMWORK

8. OPERATIONAL CONTROL CARD FOR INSTALLATION OF FORMWORK FOR COLUMNS AND SLOBS

9. OPERATIONAL CONTROL CHART WHEN INSTALLING FOUNDATION FORMWORK

10. KAPTA OF OPERATIONAL CONTROL OF STRUCTURE REINFORCEMENT

11. OPERATIONAL CONTROL CHART FOR CONCRETE PLOCKING

12. OPERATIONAL CONTROL CARD FOR WALL CONCRETE PASTING

13. OPERATIONAL CONTROL CHART FOR COLUMNS CONCRETE PATING

14. OPERATIONAL CONTROL CHART FOR BRICK PILLARS

15. OPERATIONAL CONTROL CHART FOR WALL BRICK MASONRY

16. OPERATIONAL CONTROL CARD FOR INSTALLATION OF WINDOW AND DOOR UNITS

The technological map does not replace commissioning and commissioning (see SNiP 3.01.01-85*) The quality of construction and installation work is characterized by the degree of their compliance with the requirements of the projects and SNiP. Any deviation from these requirements must be detected and corrected in a timely manner, which can only be achieved through routine operational quality control. Operational quality control of construction and installation works is carried out by the work producer and the foreman, with the involvement, if necessary, of representatives of the quality management laboratory of the trust (association). The main tasks of operational quality control of construction and installation works: - ensuring the required level of quality of buildings being constructed; - ensuring the execution of construction and installation work in accordance with the project and the requirements of regulatory documents; - timely identification of the causes of defects during the production of work and taking measures to eliminate them; - increasing the personal responsibility of direct performers and line engineering and technical workers for the quality of construction and installation work performed. All defects identified during operational control must be eliminated before subsequent operations (work) begin. Operational control must be carried out in strict accordance with the enterprise standard (STP) “Regulations on operational quality control”. The main documents of operational quality control are operational control cards. They must be constantly kept at the construction site by the construction manager and presented at the request of persons monitoring the quality of work. They indicate the responsibilities of officials when exercising operational control. If work at the site is headed by one manager (foreman, foreman), then he performs all control functions specified in the operational control cards. Operational quality control cards are intended for line engineering and technical workers and foremen, and can also be used by persons exercising construction quality control.

1. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE COLUMNS

Tolerances for the installation of reinforced concrete columns in accordance with the requirements of SNiP 1. Difference in elevations of the tops of adjacent columns or support platforms (brackets, consoles) ± 10 mm 2. Difference in elevations of the tops of columns or support platforms within the verified area: with contact installation 12+2, where - serial number of the tier when installed along beacons 10 mm 3. Displacement of the axes of columns of one-story buildings in the upper section from the vertical at column height H: in meters up to 10 m ± 10 mm over 10 m 0.001 N, but not more than 35 mm 4. Displacement of the axes of columns multi-storey buildings in the upper section relative to the alignment axes for columns with a height of: up to 4.5 m ± 10 mm over 4.6 m ± 15 mm

Table 1

Operations subject to control

Composition of control

Control method

Control time

Works

Activated works

Producer of works

Preparatory work

Correct storage

Visually

Before installation begins

Marking the bottom of the foundation glass

Using a level

Before installation begins

Surveyor

Installation of columns

Reliability of slinging, vertical installation, alignment; reference pad marks; temporary fastening

Visually; using a level; using a theodolite

During installation

Surveyor

Welding metal parts

Quality of welds

Visually

During installation

Anti-corrosion protection of metal parts

Visually

During installation

If necessary, laboratory

Embedding of columns

Thoroughness of embedding

Visually

During installation

Preparatory work(reception of structures)

Availability of passports, drawings, geometric dimensions, external defects, application of alignment axes, marks, dimensions of support areas, correct location of embedded parts

Visually; using a steel meter

Before installation begins

Preparing column installation sites

Cleaning the glasses, dimensions of the foundation glass; presence of scratches on the foundation

Before installation begins

Installation of mounting equipment

Equipment fixation accuracy

Visually

During installation

Welding of metal parts

Compliance with the project; welding of electrodes; seam sizes

Visually

During installation

Laboratory

Embedding columns in foundations

Brand, consistency of concrete mixture, thoroughness of compaction

Visually, using a standard cone

During installation

Laboratory

2. OPERATIONAL CONTROL CARD FOR INSTALLATION OF LARGE BLOCK STRIP FOUNDATIONS

Tolerances for the installation of large-block strip foundations in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of foundation blocks and foundation wall blocks relative to the alignment axes ± 10 mm 2. Deviation of marks of the upper supporting surfaces of foundation elements - 10 mm 3. Displacement of axes or faces wall blocks in the lower section relative to the alignment axes or geometric axes below installed structures± 5mm

table 2

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Determination of soil conditions

Visually

Before installation begins

The correct location of the pit relative to the alignment drawing, the reliability of fastening, and the mark of the bottom of the pit

Visually, using a level and tape measure

Before installation begins

Surveyor

Marking the top of the sand or gravel bed

Using a level

Before installation begins

Surveyor

Correct storage

Visually

Before installation begins

Layout of foundation axes

Accuracy of determining the position of building corners. Compliance with the design of the distances between the axes of prefabricated foundations

Using a theodolite and tape measure

Before installation begins

Surveyor

Installation of foundation blocks

Visually

During installation

Accuracy of installation, foundation blocks. Density of support and abutment

Using a level and plumb line

During installation

Compliance of marks with design

Using a level

After installing the blocks

Surveyor

Preparatory work

Adequacy of pit sizes

Using a tape measure

Before installation begins

The thickness of the sand or gravel cushion, the quality of its compaction

Visually, using a steel meter

Before installation begins

Cleaning foundation blocks from dirt and snow in winter

Visually

Before installation begins

Availability of passports for reinforced concrete structures; compliance of the geometric dimensions of the blocks with the project; external defects

Roulettes

Before installation begins

Layout of foundation axes

Correct tension of axes, accuracy of intersection of axes on foundation blocks

Using a theodolite

Before installation begins

Surveyor

Installation of foundation blocks

Compliance with installation technology, technological map

Visually

During installation

3. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE FOUNDATIONS UNDER COLUMNS

Installation tolerances reinforced concrete foundations for columns in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of the foundation glasses relative to the alignment axes ± 10mm 2. Deviation of the marks of the upper supporting surfaces of the foundation elements - 10mm 3. Deviation of the marks of the bottom of the foundation glasses - 20mm

Table 3

Operations subject to control

Composition of control

Control method

Control time

Activated works

Producer of works

Preparatory work

Preparation of the base for foundations, its condition, dimensions, marks, protection against freezing in winter

Using a level, steel meter, tape measure

Before installation begins

Surveyor

The dimensions of the pits, the correctness of their location and the reliability of fastening the walls of the pit, the marks of the bottom of the pit

Visually, using a level, tape measure, plumb line

Before installation begins

Marking the top of the base and leveling the pillow

Using a level

Before installation begins

Surveyor

Lateral waterproofing of foundation blocks

Insulation quality

Visually

After installation

Preparatory work

The thickness of the sand or gravel bed and the quality of its compaction

Visually i using a steel meter

Before installation begins

Cleaning from dirt, snow and ice in winter

Visually

Before installation begins

Checking the geometric dimensions of blocks, defects. Comparison of passport data of reinforced concrete structures with design data

Before installation begins

Installation of control sights along the axes of foundations

Compliance with the design of the axles transferred to the bottom of the pit.

Accuracy of the position of the top of the control sights

Using a theodolite or level

Before installation begins

Installation and alignment of blocks

Installation accuracy, compliance with design marks and axes

Using a level, reference

During installation

Surveyor

4. OPERATIONAL CONTROL CARD WHEN INSTALLING BEANS

Tolerances for the installation of crossbars in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of the crossbars along the lower chord relative to the geometric axes supporting structures ± 6 mm 2. Deviation of distances between the axes of the crossbars at the level of the upper chords ± 20mm 3. Tolerances of support areas and tolerances of gaps between elements are determined by the project

Table 4

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Correct storage of structures

Visually

Before installation begins

Alignment of supporting surfaces on columns

Compliance of the elevations of the supporting platforms of the columns with the design ones, the correctness of the alignment axes

Using a theodolite, level, steel meter

Before installation begins

Surveyor

Installation of crossbars

Correctness and reliability of slinging

Visually

During installation

Alignment of crossbar axes with alignment axes on supporting structures, verticality and tightness of support of the crossbar

Visually, using a plumb line

During installation

Welding of embedded parts at joints

Visually, using a steel meter

During installation

If necessary, laboratory

Sealing joints

Appearance joints, strength of concrete at the joint

Visually, using a standard hammer

After stripping the joint

Laboratory

Preparatory work

Compliance of geometric dimensions with design ones, external defects, presence of passports, correct location of embedded parts, cleaning them

Visually, using a steel meter, tape measure

Before installation begins

Alignment of supporting surfaces on columns

Visually, using a steel meter

Installation of crossbars

Correct application of axial and control marks on crossbars

Visually, using a steel meter, tape measure

During installation

Visually

During installation

Compliance of the joint design and electrode brand according to the project

Visually

During installation

Sealing joints

Density and strength of formwork

Visually

During installation

Concrete grade

Before concreting

Laboratory

Joint seal quality

Visually

During the concreting process

Quality of joint filling

Visually

After stripping

5. OPERATIONAL CONTROL CARD FOR INSTALLATION OF REINFORCED CONCRETE TRUSSES AND BEAMS

Tolerances for the installation of reinforced concrete trusses and beams in accordance with the requirements of SNiP III -16-73 1. Displacement of the axes of the trusses (beams) along the lower chord relative to the geometric axes of the supporting structures ± 5 mm 2. Deviation of the distances between the axes of the trusses (beams) at the level of the upper chords ± 20 mm 3. Tolerances of support areas and tolerances of gaps between elements are determined by the project

Table 5

Quality Control Persons

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Correct storage of reinforced concrete structures

Visually

Before installation begins

Alignment of supporting surfaces of previously installed structures

Compliance of the elevations of the reference areas with the design ones, the correctness of the alignment axes

Before installation begins

Surveyor

Installation of trusses and beams

Correctness and reliability of slinging

Visually

During installation

Alignment of beam truss axes with alignment axes, verticality of support structures

Visually, using a plumb line

During installation

Reliability of temporary fastening

Visually

During installation

Welding of embedded parts at joints

Welding quality, acceptance certificates for welded joints, seam sizes

Visually, using a steel meter

During the installation process

Anti-corrosion protection

Quality of application of the anti-corrosion layer

Visually

Before embedding

If necessary, laboratory

Preparatory work

Availability of passports, geometric dimensions, external defects, reinforced concrete structures

Visually, using a steel meter

Before installation begins

Arrangement of embedded parts, cleaning them from rust and concrete deposits

Visually, using a steel meter

Before installation begins

Alignment of supporting surfaces of structures

Position of support platforms and embedded parts

Visually

Before installation begins

Installation of beam trusses

Presence and correct application of axial and control marks on structures

Using a steel meter

During installation

Correct installation technology

Visually

During installation

Welding of embedded parts at joints

Type of electrodes, compliance of the joint with the design

Visually

During installation

Sealing joints

Density and strength of formwork

Visually

Before concreting

Concrete grade, compaction quality

Visually

In the process of embedding

Laboratory

Appearance of the joint, quality of the seal

Visually

In the process of embedding

Compliance of the elevations of the installed structures with the design ones, the distance between the axes

Visually

After installation

Surveyor

6. OPERATIONAL CONTROL CARD FOR INSTALLATION OF FLOOR PANELS (COATING)

Tolerances for the installation of floor (covering) panels in accordance with the requirements of SNiP III -16-73 1. The difference in elevations of the front surfaces of two adjacent floor (covering) slabs at the joint is ± 5 mm 2. The displacement in plan of the covering or floor slabs relative to their design position on supporting surfaces and nodes of trusses and other load-bearing structures(along the supporting sides of the slabs), not allowed 3. Permissible deviations in the dimensions of the support areas and gaps between structural elements are determined by the design

Table 6

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved with control

Activated works

Producer of works

Preparatory work

Correct storage of panels

Visually

Before installation begins

Compliance of elevations and support areas with design

Using a level, tape measure, steel meter

Before installation begins

Surveyor

Installation of floor panels

Instrumental inspection of the installation horizon of each floor

Using a level

During installation

Surveyor

Anti-corrosion protection of anchors

Quality of anti-corrosion coating

Visually

Securing joints

Laboratory

Sealing joints

Quality of grouting of joints

Visually

After embedding

Preparatory work

Availability of passports, geometric exchanges, surface quality of structures

Before installation begins

Correct location of embedded parts and mounting loops

Visually, using a tape measure, steel meter

Before installation begins

Making a supporting row of brickwork by poking

Visually

Before installation begins

Making a bed from mortar

Compliance of the mortar brand with the project, the thickness of the mortar layer

Visually

During installation

Laboratory

Panel installation

Compliance with the area of ​​support, the position of the panel in plan, the tightness of the connection to the supporting surface, the correctness of the installation technology

Visually

During installation

Panel anchoring

Compliance of anchorage with project requirements

Visually

Before embedding

Sealing joints

Cleaning and moistening the joining surfaces, matching the grade of mortar or concrete to the design

In the process of embedding

Laboratory

7. OPERATIONAL CONTROL CHART FOR INSTALLING WALL FORMWORK

Tolerances when installing wall formwork in accordance with the requirements of SNiP III -15-76 1. Distance from the vertical or design inclination of the wall formwork planes and their intersection lines for wall heights up to 5m 10 mm for wall heights over 5m 15 mm 2. Displacement of the wall formwork axes : from the design position 8 mm 3. Internal dimensions of the wall formwork from the design dimensions 3 mm 4. Local irregularities of the formwork when checked with a two-meter 3 mm strip

Table 7

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Visually

Before installing the formwork

Installation of formwork

After installing the wall formwork (before it is secured)

Surveyor

Accuracy of installation of embedded parts, their fastening

Using a meter, tape measure

After installing the formwork

Preparatory work

Compliance with the design and quality of formwork panels, correct storage

Visually, using a meter

Before installing the formwork

Installation of formwork

Compliance with design dimensions, verticality

Using a meter, plumb line

During installation of formwork

Quality of formwork fastenings

Visually

During installation of formwork

Quality inner surface formwork

During installation of formwork

8. OPERATIONAL CONTROL CARD FOR INSTALLATION OF FORMWORK FOR COLUMNS AND SLOBS

Tolerances for the installation of formwork for columns and floors in accordance with the requirements of SNiP III -15-76 1. The distance between the supports of the bending elements of the formwork and the distance between the connections of vertical supporting structures from the design dimensions: per 1 m of length 25 mm for the entire span of at least 75 mm 2. Distance from the vertical or design inclination of the formwork planes and their intersection lines: per 1 m height 5 mm to the entire height of columns up to 5 m 10 mm - "- more than 5 m 15 mm to the entire height of beams 5 mm 3. Displacement of the formwork axes from the design position of the columns 8 mm - "- beams 10 mm 4. The distance between the internal surfaces of the formwork of columns, beams from the design dimensions - 3 mm 5. Local irregularities of the formwork when checking with a 2-meter lath - 3 mm

Table 8

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Determining the state of the base (for columns)

Visually

Before installing the formwork

Installation of formwork

Compliance of supporting scaffolding and scaffolding with the project, their stability and rigidity

Visually, using a steel meter, tape measure, plumb line

Before installing the formwork

Correspondence of the formwork position to the installation axes

Using a theodolite, plumb line, tape measure

During installation of formwork

Surveyor

Accuracy of installation of embedded parts

Using a steel meter, tape measure

Formwork installation ambassador

Preparatory work

Quality of formwork panels and fastenings

Visually, using a steel meter

Before installing the formwork

Correct storage of formwork elements

Visually

Before installing the formwork

Installation of formwork

Compliance with design dimensions and marks

Using a level, plumb line, level, steel meter, tape measure

During installation of formwork

The quality of the formwork surface (density in the joints of the boards)

Visually, using a 2-meter strip

During installation of formwork

Quality of formwork fastening

Visually

During installation of formwork

9. OPERATIONAL CONTROL CHART WHEN INSTALLING FOUNDATION FORMWORK

Tolerances when installing foundation formwork in accordance with the requirements of SNiP III -15-76 1. The distance from the vertical or design position of the foundation formwork planes and their intersection lines per 1 m height is 5 mm 2. Displacement of the axes of the foundation formwork from the design position of 15mm foundations for steel structures , (L is the length of the span or step of the structure, m) 3. Local unevenness of the formwork (when checked with a 2m long lath) 3 mm

Table 9

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Determining the condition of the base

Visually

Before installing the formwork

Installation of formwork

Compliance of the formwork position with the installation axes, accuracy of installation of embedded parts and their fastening

Using a theodolite, tape measure, plumb line, steel meter

After installing the formwork

Surveyor

Preparatory work

Compliance with the design and quality of formwork panels, blocks and fasteners, correct storage of formwork elements

Visually, using a steel meter

Before installing the formwork

Installation of formwork

Compliance with design dimensions and marks. Horizontal and verticality of formwork elements, quality of fastenings, quality of the inner surface of the formwork

Visually, using a level, plumb line, steel meter

During installation of formwork

10. KAPTA OF OPERATIONAL CONTROL OF STRUCTURE REINFORCEMENT

Tolerances for the reinforcement of structures in accordance with the requirements of SNiP III -15-76 1. Reinforcing steel arriving for construction must be subject to external inspection upon acceptance. measurements and control tests in cases specified in the project 2. Replacement of reinforcing steel provided for by the project is agreed with design organization 3. Before installing the reinforcement, the formwork is checked, the pads are secured to provide clearance for the protective layer equipment 4. The mounted reinforcement is secured from displacement and protected from damage during concreting 5. The displacement of the reinforcing bars when installed in the formwork should not exceed 1/5 of the largest diameter rod and 1/4 of the diameter of the installed rod 6. It is prohibited to use spacers to form a protective layer from scraps of reinforcement, wooden blocks and crushed stone
Table 10

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Acceptance of fittings

Correspondence reinforcing mesh and frames for the project (passport)

Visually

Before installation

Installation of fittings

Installation of meshes, frames, embedded parts in accordance with the project

Using a plumb line, a steel meter

During installation

Providing a protective layer

Using a steel meter

When installing formwork

Fastening joints, frames, meshes (welding, knitting)

Visually

After securing

Laboratory

Acceptance fittings

Carried out selectively. The diameter of the reinforcement and the distance between the working rods in the meshes and frames are checked.

Using a caliper and a steel meter

Before installation

Position of embedded parts

Using a steel meter

Before installation

The quality of the reinforcement fastening points in the mesh frame

Visually

Before installation

Storage of fittings

Correct warehousing and storage

Visually

Before installation

Correct slinging

Visually, using a steel meter

During installation of fittings

Installation of fittings

Compliance with the technology adopted in the technological map or commissioning work

Visually

During installation of fittings

The correct layout of the mesh, the correct fastening of the reinforcement in the formwork

Visually, using a steel meter

During installation of fittings

Correct installation of walking boards on the slab

Visually

During installation of fittings

11. OPERATIONAL CONTROL CHART FOR CONCRETE PLOCKING

Tolerances when concreting floors in accordance with the requirements of SNiP III -15-76 1. Local deviations of the concrete surface from the design when checking structures with a 2 m ± 5 mm long 2. In the marks of surfaces and embedded parts that serve as supports for metal or precast concrete elements ± 5 mm 3. In the location of anchor bolts, in in plan inside the support contour - 5 mm in plan outside the support contour - 10 mm 4. The difference in height marks at the junction of two adjacent surfaces is 3 mm

Table 11

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Quality of formwork

Visually

Before concreting

Condition of reinforcement and embedded parts, acceptance certificate of reinforcement

Visually

Before concreting

Stripping

Surface quality, compliance with hole design, geometric dimensions

Visually, using a meter

After stripping

Strength of concrete, its homogeneity, presence of cracks

Visually, ultrasonic device

After stripping

Laboratory

Preparatory work

Quality of the base, removal of the top layer during working seams, notching, washing

Visually

Before concreting

Laying concrete mixture

Concrete mix quality

Using the StroyTsNIIL cone, press

Before concreting

Laboratory

Visually

During installation

Visually

During installation

Outdoor temperature

Using a thermometer

During installation

Compaction of concrete mixture

Rearrangement step and immersion depth of vibrators

Visually

During compaction

Adequacy of vibration and thickness of concrete layer during compaction

Visually

During compaction

Caring for concrete during hardening

Using a thermometer

During hardening

12. OPERATIONAL CONTROL CARD FOR WALL CONCRETE PASTING

Tolerances for concreting walls in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or design slope to the full height: walls supporting monolithic coverings and floors ± 15mm walls supporting precasts beam structures ± 10mm 2. Horizontal planes over the entire plane of the area being verified ± 20mm 3. Local deviations of the concrete surface from the design when checking the structure with a 2 m long strip ± 5 mm 4. In marks of surfaces and embedded parts - 5 mm

Table 12

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Formwork quality

Visually

Before concreting

Compliance with the design of the base level

Using a level

Before concreting

Surveyor

Condition of fittings and embedded parts, act of acceptance of fittings

Visually

Before concreting

Stripping

Surface quality, compliance with the design of holes, openings, channels, geometric dimensions

Visually, using a steel meter

After stripping

Strength of concrete, its homogeneity, presence of supports, cracks

Using an ultrasonic device, visually

After stripping

Laboratory

Preparatory work

Quality of the base, removal of the top layer during working seams, notching, kneading, presence of waterproofing

Visually

Before concreting

Laying concrete mixture

Quality of the concrete mixture (workability, cubic strength)

Before concreting

Laboratory

Correct technology for laying concrete mixture

Visually

During installation

Correct execution of working seams

Visually

During installation

Temperature of outside air and concrete mixture (winter)

Using a thermometer

During installation

Compaction of concrete mixture

Rearrangement step and immersion depth of vibrators

Visually, using a steel meter

During compaction

Adequacy of vibration and thickness of the concrete layer during laying

Visually, using a steel meter

During compaction

Compliance with humidity and temperature conditions

Using a thermometer

During hardening

13. OPERATIONAL CONTROL CHART FOR COLUMNS CONCRETE PATING

Tolerances for concreting in accordance with the requirements of SNiP III -15-76 1. Planes and lines of their intersection from the vertical or from the design slope to the entire height of columns supporting monolithic coverings and floors ± 15 mm Same for columns supporting precast beam structures ± 10 mm 2. Horizontal planes over the entire plane of the area being verified ± 20 mm 3. Local deviations of the concrete surface from the design when checking structures with a 2 m long strip, except for supporting surfaces ± 6 mm 4. In the cross-sectional dimensions of elements + 6 mm - 3 mm 5. In marks of surfaces and embedded parts that serve as supports for metal or precast reinforced concrete elements - 5 mm

Table 13

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons or units involved in control

Activated works

Producer of works

Preparatory work

Quality of formwork

Visually

Before concreting

Compliance with the design of the base level

Using a level

Before concreting

Surveyor

Condition of reinforcement, embedded parts, reinforcement acceptance certificate

Visually

Before concreting

Stripping

Determination of surface quality, compliance with the design of geometric dimensions, correct location of embedded parts, marks of the top of columns

Visually, using a steel meter or level

After stripping

Surveyor

Determination of concrete strength, its homogeneity

Using ultrasonic devices

After stripping

Laboratory

Preparatory work

Determining the quality of the base (cleaning from dirt, ice, snow, etc.)

Visually

Before concreting

Laying concrete mixture

Determination of the quality of the concrete mixture (mobility, cubic strength)

Using StroyTsNIIL cone, press (PSU-500)

Before installation into the structure

Laboratory

Compliance with concrete mix laying technology

Visually

During installation

Compaction of concrete mixture

Control of temperature of outside air and concrete mixture (in winter)

Using a thermometer

During installation

Compliance with the rearrangement step and immersion depth of the vibrators, the correct installation

Visually, using a steel meter

During compaction

Determining the sufficiency of vibration and the thickness of the concrete layer

Visually, using a steel meter

During compaction

Care concrete mixture during hardening

Compliance with humidity and temperature conditions

Using a thermometer

During hardening

Laboratory

14. OPERATIONAL CONTROL CHART FOR BRICK PILLARS

Tolerances for bricklaying pillars in accordance with the requirements of SNiP III -17-78 1. Deviations from the design dimensions: in thickness 10mm in marks of edges and floors 10mm in displacement of the axes of structures 10mm 2. Deviation of surfaces and corners of masonry from the vertical: per floor 10mm for the entire building 30mm 3. Irregularities on the vertical surface of the masonry, detected when applying a 2m long 5mm strip

Table 14

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Correct alignment of pillars to alignment axes

Visually, using a plumb line

Before laying begins

Brickwork pillars

Determining the correct masonry technology and bandaging the seams

Using a plumb line, a steel meter, visually

In the process of laying

Determination of compliance with the actual position of the performed brick pillars project, alignment of pillars of different floors

Visually, using a plumb line, steel meter

In the process of laying

Marking the edges of brickwork and floors, correct installation of cushions under beams, support of beams on cushions and their embedding in masonry

Visually, using a level, steel meter

After installing the pillow and installing the beam

Surveyor

Preparatory work

Determining the base for the pillars, the presence of waterproofing

Visually

Before laying pillars

Determination of the quality of bricks, reinforcement, embedded parts

Visually, by measurement, checking passports and certificates

Before laying pillars

Laboratory

Brickwork pillars

Dimensions, filling and dressing of sutures;

Using a steel meter

After completing every 5m of masonry

Geometric dimensions of the pillar cross-section

Using a steel meter

During the masonry process

Verticality of masonry, unevenness on the surface

Using a plumb line, a rod, a steel meter

After finishing laying the pillar to the height of the floor

Masonry reinforcement

The correct location of the reinforcement, the distance between the grids along the height of the column, the diameter of the rods and the distances between them

Using a steel meter, caliper

As the reinforcement is laid

15. OPERATIONAL CONTROL CHART FOR WALL BRICK MASONRY

Tolerances for bricklaying walls in accordance with the requirements of SNiP III -17-78 1. Deviation from the design dimensions; by thickness 15 mm by marks of edges and floors 10 mm by width of partitions 15 mm by width of openings 15 mm by offset of adjacent axes window openings 20 mm for the displacement of the axes of structures 10 mm 2. Deviations of surfaces and corners of masonry from the vertical: for one floor 10 mm for the entire building 30 mm 3. Deviations of rows of masonry from the horizontal for 10 m of length 15 mm 4. Irregularities on the vertical surface of masonry, detected when applying a 2-meter 10 mm strip

Table 15

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Brickwork walls

Quality of bricks, mortar, fittings, embedded parts

External inspection, measurements, verification of passports and certificates

Before laying the walls of the floor

In case of doubt - laboratory

Correct axle alignment

Using a steel tape measure, meter

Before laying begins

Horizontal marks of masonry trims for the ceiling

Using a level, staff, level

Before installing floor panels

Surveyor

Alignment ventilation ducts and sealing of ventilation units

Visually, using a plumb line

After finishing the laying of the floor walls

Masonry reinforcement

Correct placement of reinforcement, diameter of rods, etc.

Visually, using a steel meter

Before installing fittings

Installation of prefabricated reinforced concrete slabs floors

Supporting slabs, caulking, anchoring

Visually, using a steel meter

After installing the ceiling

Anti-corrosion coating of embedded parts

Thickness, density and adhesion of the coating

Visually, using a thickness gauge, engraving pen

Before sealing

Laboratory

Installation of balconies

Sealing, marking, slope of balconies

Using a steel meter, level, 2-meter rod

After installing balconies

Brick walls

Geometric dimensions of masonry

Using a steel tape measure, meter

Verticality, horizontality and masonry surface

Using a level, staff, plumb line

During and after finishing the laying of floor walls

Quality of masonry seams

Using a steel meter, 2 meter rod

After completing every 10m 3 masonry

Layout and markings of the bottom of openings

Using a steel tape measure. level, level

Before laying the walls begins

Removal of the mark + 1 m from the finished floor

Using a level

After completing the laying of the floor

Apartment layout

Visually

After starting to lay the walls

Geometric dimensions of premises

Using a steel tape measure

After starting to lay the walls

Installing jumpers

Jumper position, support, placement, termination

Visually, using a steel meter

After installing jumpers

Installation landings

Position of pistillate sites, support, placement, embedding

Visually, using a steel meter

After installing the platforms

Welding of embedded parts

Length, height, quality of welds

Visually, tapping with a hammer

Before anti-corrosion coating

Soundproofing device

Design, quality of workmanship

Visually

Immediately after finishing work

16. OPERATIONAL CONTROL CARD FOR INSTALLATION OF WINDOW AND DOOR UNITS

Rules for installing window and door units in accordance with the requirements of SNiP III -19-76 1. The surfaces of window and door units adjacent to stone walls are antiseptic with waterproofing materials 2. The gaps between the frame and the masonry of the external walls are sealed thermal insulation materials 3. Window and door frames in stone walls and partitions are secured with screws or steel brushes driven into antiseptic wooden plugs. Each vertical block of the box is secured in at least 2 places, the distance between them does not exceed 1 meter
Table 16

Quality Control Persons

Operations subject to control

Composition of control

Control method

Control time

Persons involved in control

Activated works

Producer of works

Preparatory work

Appearance, factory readiness, compliance with standards, Unified Regulations and Design, completeness of delivery of window and door units, availability of antiseptic certificates

Visually

When accepting blocks

Availability of antiseptic plugs for attaching blocks

Visually

Before installing blocks

Transportation and storage conditions

Visually

On construction site

Installation of door and window blocks

Correct installation at a given elevation and along a given axis

Using a level, plumb line, tape measure

After installing the boxes

Fastening boxes

Visually

After installing the boxes

Fit tightness of window and door frames

Visually

After installing the boxes

Waterproofing the junction of blocks and masonry

Visually

After installation

Caulk with thermal insulating material sealed with sealant. Coating the joints between blocks and masonry with mortar

Visually

After installing the box

The gap between the floor surface and door leaf

Using a steel meter

After installing the box

Installation of window sill boards

The presence of teardrops in wooden window sill boards

Visually

Before installing window sill boards

Antiseptic and insulation of the bottom surface board wooden window sills

Visually

Before installing window sill boards

Sill board slope

Using a rod, level, steel meter

After installing window sill boards

Platband overlay on the wall

Using the steel metro


page 1



page 2



page 3



page 4



page 5



page 6



page 7



page 8



page 9



page 10

CENTRAL

SCIENTIFIC AND RESEARCH ED O VAT EL SKI AND DESIGN AND EXPERIMENTAL INSTITUTE OF ORGANIZATION, MECHANIZATION AND TECHNICAL ASSISTANCE TO CONSTRUCTION OF THE USSR GOST CONSTRUCTION

ON IMPLEMENTATION

OPERATING

CONTROL

MOSCOW - 1973

CENTRAL

SCIENTIFIC RESEARCH AND DESIGN AND EXPERIMENTAL INSTITUTE OF ORGANIZATION, MECHANIZATION AND TECHNICAL ASSISTANCE TO CONSTRUCTION OF THE USSR State Construction Agency

ON IMPLEMENTATION

OPERATING

CONTROL

Moscow - 1973

QUALITY OF CONSTRUCTION INSTALLATION WORKS

PUBLISHING HOUSE OF LITERATURE ON CONSTRUCTION

Recommendations for the implementation of operational quality control of construction and installation works were developed by the TsNIIOMTP Gosstroy of the USSR (performed by engineer E.M. Zolotnikov), NIISP Gosstroy of the Ukrainian SSR (executed by engineer L.I. Pokrass).


Plan If-III k". 1971, M 14


1. These Recommendations establish a general procedure for operational quality control of construction, installation and special construction work during the construction of buildings and structures for various purposes, built in ordinary areas and in areas with special natural conditions(seismic, distribution of permafrost subsidence and other soils, etc.).

2. Recommendations are mandatory for construction, installation and specialized construction organizations regardless of their departmental subordination, as well as for technical supervision of the customer (developer), designer supervision of design organizations.

3. The main objectives of operational quality control of construction, installation and special construction works are:

ensuring compliance of the construction, installation and special construction work performed with the project and the requirements of regulatory documents for construction. approved or agreed upon by the USSR State Construction Committee;

timely identification of the causes of defects during the production of work and taking measures to eliminate them;

increasing the responsibility of direct performers (working units, teams) for the quality of work.

4. Operational quality control of construction and installation work is assigned to the work producers and craftsmen who manage the construction of buildings and structures.

In necessary cases, construction laboratories and geodetic and surveying services, as well as specialists involved in the control of certain types of work, are involved in operational control;

carried out in accordance with the schemes of operational quality control of work performance (SOKK),

attached to the technological maps, which are integral part work projects (WPP). approved by engineers of construction and installation or specialized construction organizations in accordance with the Instructions on the procedure for drawing up and approving. requirements for construction organization projects and work production projects (SN 47-67), approved by the USSR State Construction Committee.

For the construction of facilities for which technological maps are not developed, production preparation and work design groups of construction organizations are required to issue standard or re-use SOKK.

5. The compilation of the SOKK is carried out on the basis of the requirements of regulatory documents for construction and state standards.

6. SOKK must contain:

sketches of structures indicating permissible deviations according to SNiP, and, if necessary, the main characteristics of the quality of the material or structures (strength, frost resistance, fire resistance, etc.);

a list of operations the performance of which must be checked by the workman or foreman;

data on the composition of the control established on the basis of the requirements of regulatory documents for construction and working drawings indicating what needs to be checked (for example, the cross-section of reinforcement and the location of reinforcing bars; compliance of the actual dimensions of elements with the design ones; embedding of floor slabs and coatings, their connection with each other , as well as with harnesses and anti-seismic belts, etc.);

an indication of the method of monitoring the operations being performed - how and by what means the check should be carried out (visually, instrumentally - name measuring instruments and tools, etc.);

timing of control;

a list of hidden work to be submitted to representatives of the technical supervision of the customer (developer);

redesign of operations controlled with the participation of the construction laboratory, geodetic and surveying service (compliance with the geometric parameters of the project, accuracy of transfer of design data into nature

etc.), as well as specialists involved in monitoring certain types of work;

The diagram is drawn in a 420X297 mm format, which is reduced when reprinted to the required size.

An example of SOKK is given in the appendix.

7. The list of hidden work to be submitted to representatives of the customer’s technical supervision is determined by the compilers of the SOKK based on SNiP and other regulatory documents, and the sequence of delivery of hidden work is indicated (for example, welding of embedded parts before the production of anti-corrosion protection, etc.).

Note. The specified list must necessarily include work on laying reinforcement outlets (anchors) in foundations, supports, and ceilings for the purpose of using them in the construction of anti-seismic belts.

8. When determining the list of operations controlled with the participation of a construction laboratory, geodetic and surveying service, as well as specialists involved in the control of certain types of work, one should be guided by the current Standard Regulations on laboratories of construction and installation organizations and their manufacturing enterprises, Regulations on the geodetic and surveying service in construction organizations and other regulatory documents approved or agreed upon by the USSR State Construction Committee.

9. SOKK are developed according to orders of contract construction organizations by the Orgtekhstroy (Org-Stroy) trusts, preparation and design groups for the production of construction and installation works and specialized construction organizations, and for experimental construction - by design and research institutes.

10. The management of a construction and installation or specialized construction organization, no later than 15 days before the start of work, must transfer to the immediate supervisor of the construction of a building or structure (work foreman, foreman) the SOKK complete with PPR and technological maps. SOKK must be presented at the request of persons monitoring the quality of construction.

11. The start of construction, installation and special construction work must be preceded by an inspection

work producers and craftsmen with the participation, where necessary, of representatives of construction quality laboratories building materials, products, semi-finished products, structures (as they are received for construction), as well as compliance of these passports and certificates with the requirements of the projects.

12. All defects identified during operational control (deviations from projects, standards, requirements of regulatory documents for construction) must be eliminated before the start of subsequent operations (work).

13. The organization of operational control and the establishment of supervision over its implementation is entrusted to the heads and chief engineers of construction, installation and specialized construction organizations (sites, departments, trusts, etc.).

14. Chief engineers of construction, installation and specialized construction organizations are obliged to ensure, before starting work at the site:

instructing line engineering and technical personnel of construction sites and workshops on the procedure for conducting operational control, documented by a corresponding entry in the log of work on the construction of the facility;

studying by all engineering and technical employees and workers the requirements of SNiP when performing construction and installation work in areas with special natural conditions, testing the knowledge of these workers, documenting the results of this test;

instructing newly hired engineering and technical workers on the procedure for operational control of the quality of work.

15. Engineering and technical workers carrying out operational quality control of construction and special construction works are required to keep records of production defects and defects identified during the said control and enter them into the logs of construction work.

APPLICATION

OPERATIONAL QUALITY CONTROL SCHEME

(Installation of foundation formwork)

1 - deviations internal dimensions(length, width) of building foundation glasses - 15 mm; 2 - deviations of ledges in plan -20 mm; 3 - deviations from horizontal ±5 mm;

4 - deviations in the location of holes for connecting elements(wedges, bolts, etc.) - 0.5 mm;

5 - offset relative to the alignment axes of the bottom row ±20 mm;

6 - displacement relative to the alignment axes of the glasses and blocks of the top row ±110 mm; 7 - permissible deviation of the top of the foundations ±5 mm;

I - deviations of the marks of the supporting surfaces of the foundations from the design ones - 20 mm; P - deviations from the vertical or from the design inclination of the formwork planes over the entire height of the foundation - 20 mm, per 1 m height - 5 mm; /0 - deviations of foundation edge marks ±15 mm; L - deviations in the length and width of panels and frames for

them - b mm.

Note. If work at the site is headed by one manager (foreman or foreman), he performs all control functions according to the scheme.

Operations,

What is controlled

How to con-

current con-

polished

control-

o fc O.^2<о

Compliance with the project and quality of formwork panels, blocks and fasteners, geometric

Visually, steel meter

Before installing the formwork

all sizes

workers

elements, condition

formwork materials Correct storage

hazard elements

About before false

Operation subject to control

What is controlled

How is it controlled?

controls

formwork

Compliance with the design marks of the ledges, the top of the formwork, the bottom of the glasses, the dimensions of the ledges, the horizontal and vertical position of the formwork

steel

During the installation of tiered formwork

Quality of formwork fastenings, fastening of formwork, making connections

Quality of the inner surface of the formwork, removal of debris, ice

Foundation condition

Before installing the formwork

Installation of formwork

Correspondence of the position of the lower tier of the formwork to the installation axes

Theodolite,

steel

After installing the lower tier before securing

Installation of formwork

Correspondence of the position of the upper tier and the glass to the installation axes

Theodolite,

steel

After installing the formwork, upper tier and glass

Accuracy of installation of embedded parts and their fastening

Steel

After installing the formwork

Moskaa, K-31, Kuznetsky Most, 9, Stroyizdat 0

Editor of the publishing house V. V. Petrova Technical editor K. E. Tarkhova Proofreader M. F. Kazakova

Submitted for printing on November 22, 1972. Signed for printing on December 13, 1972. T-20 236 Printing paper No. 2 84X108"/* - 0.126 paper l.

0.42 el. oven l. (ed. 0.4 l.)

Circulation 50,000 copies. Ed. No. XII-3936 Order. Ni 463 Price 3 kopecks.

Podolsk printing house of the Main Printing Industry of the State Committee of the Council of Ministers of the USSR for Publishing, Printing and Book Trade Podolsk, st. Kirova, 25

Share